Venice
ProjectDet::Update
 
Updates a Project Detail.
 
void Update (
    enum eUpdateMode eUpdateMode
)
 
Parameters
eUpdateMode
[in] A value of the 'eUpdateMode' enumeration.
 
Remarks
A project detail cannot be updated using the update mode umDialog. Otherwise, an exception will be thrown!
Updating a record destroys the object positioning that was previously established via a SeekBy-method and the GetNext/GetPrevious-methods. The results of calling GetNext or GetPrevious after an update are not guaranteed.
 
See Also
CreateProjectDet
SeekBySysNum
SetFieldVal
 
Samples
 
C++
 
// Update the action date of the last inserted project detail to 26/04/2024
if (pProjectDet->SeekBySysNum (smLast, 0))
{
    VARIANT vActionDate;
    vActionDate.vt = VT_DATE;
    vActionDate.date = COleDateTime (2024, 4, 26, 0, 0, 0).m_dt;
    pProjectDet->SetFieldVal (pjdfActionDate, vActionDate);
    pProjectDet->Update (umFullReport);
}

C#
 
// Update the action date of the last inserted project detail to 26/04/2024
if (oProjectDet.SeekBySysNum (eSeekMode.smLast, 0))
{
    oProjectDet.SetFieldVal (eProjectDetFld.pjdfActionDate, new DateTime (2024, 4, 26));
    oProjectDet.Update (eUpdateMode.umFullReport);
}

VBS
 
' Update the action date of the last inserted project detail to 26/04/2024
If oProjectDet.SeekBySysNum(smLast, 0) Then
    Dim dtActionDate
    dtActionDate = #4/26/2024#
    Call oProjectDet.SetFieldVal(oProjectDet.GetFieldID("ActionDate"), dtActionDate)
    Call oProjectDet.Update(umFullReport)
End If

VB.NET
 
' Update the action date of the last inserted project detail to 26/04/2024
If oProjectDet.SeekBySysNum(eSeekMode.smLast, 0) Then
    Dim dtActionDate As Date
    dtActionDate = #4/26/2024#
    oProjectDet.SetFieldVal(eProjectDetFld.pjdfActionDate, dtActionDate)
    oProjectDet.Update(eUpdateMode.umFullReport)
End If